Brian Perry Civil's work on the massive new Winstone Wallboards facility in Tauranga is now complete, 18 months after breaking ground.

Our team has delivered 11,000m³ of concrete, 1380t of reinforcing steel, and 520 CFA piles to provide a solid foundation for the facility.

Project Manager Ravi (FCC) Ramlagan Ramlagan says the crew “earned respect from every contractor on site, including the head contractor and client”.

“We had our share of ups (reaching milestones and delivering world-class structures) and our downs (Covid delays and resource issues), but through all the adversity BPC rose to the challenge and came out stronger”.