First Avenue Piling
List all
 

Currently two weeks behind on a three week programme.  Work got off to a slow start with a delay to delivery of pile cages and some excavated spoil on site.  The site is proving to be a challenge to the team as it is a small site and there isn't a lot of room to move.  The issue has been exacerbated as spoil removal was made the responsibility of the client and it has been difficult to get the soil removed quickly enough which is impacting the piling program.  Clearing the spoil away from the bore hole got delayed and even preparation for the next pile drilling.  A few days of heavy rain didn't help which caused a bit of a mess on site.  The sun is out, the team has had a good clean up on site and progress has improved.