| Poutu Canal Joint and Invert Repairs |
| Client: Genesis Ltd |
Location: Turangi |
| Engineer: Genesis Power Ltd |
Main Contractor: Brian Perry Civil |
| Value: $2.8 million |
Completed: December 2008 |
Click image(s) to enlarge
The contract was suspended for 3 months due to Genesis Power Ltd generation needs in the middle of the contract.
Works included:
- Design and install a cofferdam in the tunnel upstream of the canal intake.
- Provide and operate dewatering facilities to enable work within the canal to proceed in the dry.
- Excavate and clear silt, gravel and debris from the canal - approx volume 1400 cubic metres.
- Water-blast concrete slab invert area to remove loose scale, moss and grime including capture, diversion treatment and disposal of contaminated blast water - canal length 6km.
- Complete joint repairs allowing for 17 litres of joint sealant per transverse joint - 185no.
- Form, cast and finish 100mm and 150mm thick concrete overlay slab including joints and surface treatment - 35,000 sq metres.
View more gallery images |
|
|
|
- We are very pleased to announce that on Friday evening we won the premium award for the $5m to $20m category in the Hirepool NZCF awards for the Waiwhetu Stream Project more >>
- Brian Perry Civil has been awarded the Ingenium Excellence Award for the Achilles Point Lookout and Reserve Project. more >>
- The Cliff Road Retaining Wall project carried out in St Heliers, Auckland won the 2009 NZCF Hirepool Award in Category 3.... more >>
- The Waitakere Dam Upgrade Project won the 2009 Environmental Award in Category 2 ($500 to $2m) more >>
|
|
View All >> |
|
 |
|
|
 |
 |
| The Fletcher Construction Company Limited trading as Brian Perry Civil |
|
| |
|
|